Non-Disruptive Power Circuit Maintenance - New York
Scheduled Maintenance Report for Equinix Metal
Completed
The scheduled maintenance has been completed.
Posted Sep 07, 2021 - 22:55 UTC
Update
There was brief, unexpected impact to a subset of customers in scope of this maintenance which has been resolved at this time.

If you are still experiencing impact or need further support, please reach out to support@equinixmetal.com for further assistance.
Posted Sep 07, 2021 - 22:33 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 07, 2021 - 21:05 UTC
Scheduled
On Tuesday, September 7, 2021 from 5:05 PM to 08:05 PM EST (905 - 1205 UTC), we will implement a non-disruptive power circuit maintenance for several racks in our EWR1 facility.

During the maintenance, engineers will cut secondary connections over to new circuits which extend to a redundant power supply in the Data Center. This process has been designed as non-disruptive; however engineers will be on-site to ensure any unexpected impact is resolved as quickly as possible.

If you have infrastructure that is in the scope of this upgrade, a direct notification via email will be sent to the maintenance email address listed within your Equinix Metal organization. Please reach out to our support team at support@equinixmetal.com if you have any questions or concerns.
Posted Aug 30, 2021 - 16:00 UTC
This scheduled maintenance affected: Americas (New York (NY)).