Shared Interconnection Maintenance - LD Metro

Scheduled Maintenance Report for Equinix Metal

Completed

The scheduled maintenance has been completed.
Posted Aug 19, 2025 - 05:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 18, 2025 - 21:00 UTC

Scheduled

On Monday, August 18th, 2025 between 21:00 UTC and August 19th 05:00 UTC, a subset of Equinix Metal Shared Fabric interconnections will be impacted by a maintenance activity in the Fabric Network and/or its underlying providers.

Some customers with redundant interconnections will see impact on primary virtual circuits only. Redundant secondary virtual circuits will remain in operation. Customers with non-redundant interconnections may see mixed impact on their virtual circuits.

Metros in the scope of this maintenance: London

Please reach out at support@equinixmetal.com with any questions.
Posted Aug 05, 2025 - 23:36 UTC
This scheduled maintenance affected: EMEA (London (LD)) and Equinix Metal Network.