Planned Network Maintenance - SE Metro
Scheduled Maintenance Report for Equinix Metal
Completed
The scheduled maintenance has been completed.
Posted Aug 14, 2024 - 06:16 UTC
Verifying
Verification is currently underway for the maintenance items.
Posted Aug 14, 2024 - 05:45 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 14, 2024 - 04:00 UTC
Scheduled
On Wednesday, August, 14th between 04:00 and 09:00 UTC, we will perform a scheduled network maintenance.

Customers with servers configured with unbonded network modes may lose connectivity to some services for approximately 30 minutes as switches are upgraded. Customers with properly configured bonded modes should not lose connectivity but should see impact on individual bond member nics at separate times.

Customers with redundant interconnections will see impact on primary virtual circuits only. Redundant secondary virtual circuits will remain in operation. Customers with non-redundant interconnections may see mixed impact on their virtual circuits.

Metros in the scope of this maintenance: Seattle.

Please reach out at support@equinixmetal.com with any questions.
Posted Jul 26, 2024 - 08:02 UTC
This scheduled maintenance affected: Equinix Metal Network and Americas (Seattle (SE)).