Planned Network Maintenance - FR Metro

Scheduled Maintenance Report for Equinix Metal

Completed

The scheduled maintenance has been completed.
Posted Jun 19, 2025 - 02:34 UTC

Verifying

Verification is currently underway for the maintenance items.
Posted Jun 19, 2025 - 01:18 UTC

Update

During one of the transitions, we experienced an ungraceful traffic shift that caused routing instability for a couple of minutes. The issue was resolved quickly, but a subset of customers may have experienced some packet loss during this time.
Posted Jun 18, 2025 - 23:27 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 18, 2025 - 22:00 UTC

Scheduled

On Wednesday, June 18th, 2025, between 22:00 UTC and Thursday, June 19th, 03:00 UTC, we will perform a scheduled network maintenance. This includes backbone-level route adjustments, non-impacting network infrastructure decommission, and capacity enhancements.

Customers with redundant interconnections may experience an impact on primary shared and dedicated circuits for approximately 30 minutes as devices are upgraded. Redundant secondary shared and dedicated circuits will remain in operation. Customers with non-redundant interconnections may see mixed impact to their shared and dedicated circuits.

Metros in the scope of this maintenance: Frankfurt.

Please reach out at support@equinixmetal.com with any questions.
Posted May 28, 2025 - 01:11 UTC
This scheduled maintenance affected: EMEA (Frankfurt (FR)) and Equinix Metal Network.